HCC Property Development Update
We are presently forming a building task force whose role will be to provide input, perspective, and wisdom for the future facility of HCC under the guidance of the HCC Council.
The following will be the 4 goals this task force will be focused on:
Potential timeline:
June 30 - HCC building task force in place
July and August - Interview and select an architectural firm
September - The design process started
December 30 - Preliminary drawings completed
Continue to pray with us during this season as we move forward in providing a permanent location for HCC. If you would like to suggest someone's name for the HCC building task force, please send an email to [email protected]
See you on Sunday!
The following will be the 4 goals this task force will be focused on:
- Interview and hire an architectural firm.
- Determine a timeline for the completion of the project.
- Work directly with the architect during several phases of designing the building and planning the site.
- Help keep HCC informed of critical information concerning the project.
Potential timeline:
June 30 - HCC building task force in place
July and August - Interview and select an architectural firm
September - The design process started
December 30 - Preliminary drawings completed
Continue to pray with us during this season as we move forward in providing a permanent location for HCC. If you would like to suggest someone's name for the HCC building task force, please send an email to [email protected]